highway improvement works fann street

Highway improvement works will take place on Fann Street, along the northern footway beside the Golden Lane Estate, starting on Tuesday 26 May 2026.

WHAT’S HAPPENING

  • Removal of existing concrete planters and asphalt
  • Installation of three raised planting beds
  • Creation of two new pathways using resin-bound gravel
  • Final planting to be completed in Autumn, to accommodate planting seasons

Programme duration: Approx. 8 weeks
Contractor: FM Conway (City Corporation term contractor)

PROGRAMME

  • Week 1 – 3: Site preparations including clearance and excavations
  • Week 4: Installation of steel and soil delivery 
  • Week 5 – 8: Reinstatement, laying channels and surfacing works

Planting will be delivered in Autumn 2026 to take account of the planting seasons and ensure water connections are installed.

WORKING HOURS

  • Monday-Friday: 08:00-18:00
    (Noisy works restricted between 10:00-12:00 and 14:00-16:00)
  • Saturday: 09:00-14:00

The work area will be safely barriered off throughout construction.

CONTACT FOR DAY-TO-DAY CONSTRUCTION QUERIES
Georgia Errington 07523 437173 or FM Conway Customer Care Team 01732 600888

Project enquiries: environmental.resilience@cityoflondon.gov.uk

We will make every effort to minimise disruption and apologise for any inconvenience caused.