major works committee report

On 17 April 2024 a progress report on the Housing Major Works Programme was presented to the Housing Management and Almshouses Sub Committee. The report covers Major Works projects across the Corporation social housing portfolio.

H40a – Window Refurbishment, Roofing, Ventilation and Heating (Crescent House)

Listed Building Consent and Planning application for the whole block has now been approved. The project requires the tender documents to be finalised and this has slipped due to internal delays setting up the budgets. The tender will not be advertised until early may once the pricing document has been finalised and specific planning conditions discharged.

H40b,c,d,e – Window Refurbishment, Roofing, Ventilation and Heating (Golden Lane Estate – Remaining Blocks)

Much of the design work for Stanley Cohen and Cullum Welch is now complete but awaits some final pieces of work to be completed such as structural surveys and embodied carbon assessments. There has been a delay in setting up the budgets, so this work is on hold until the relevant consultants can be instructed to complete this piece of work.

– 17 April 2024 ‘Housing Major Works Programme – Progress Report’