hatfield podium | notes from resident briefing

Hatfield Podium Works
Last week GLERA organised a resident briefing with VolkerLaser’s Project Manager, Ehsan Fathiazar, and CoL Project Manager, Dean Elsworth, who explained:

  • the reason for the project
  • how we can get across the estate
  • how the site will be accessed
  • where the site facilities and storage will be
  • how they will be dealing with noisy work

Below the key points from the meeting. Their communications consultant (CommComm UK) have promised an update.

key points

PROGRAMME

  • Site set up starts Monday 24 November
  • Christmas shut down 23 December to 5 January
  • The project runs until April 2026

ACCESS

  • UPDATE: Since contractors have been on site they find they can now keep North South access from under Hatfield across the estate open for much of the project. There will be a couple of weeks in February when this will no longer be the case
  • There will be 2 phases to make sure that the East West access is maintained
  • For 2 weeks in February SRPC will need to be accessed through the allotments
  • Access to the allotments will be via Basterfield service road gate – a key box and key will be provided
  • The children’s playground will be closed for the duration UPDATE: contractors are now trying to find away around this

NOISY WORKS

  • Scaffolding will be erected along the line of the grass and outside the leisure centre to carry a moving roof to protect the works (2-10 Dec will be noisy)
  • The noisiest work (breaking up the concrete) will take about 3 weeks in total from the end of December into January.
  • The area will be fenced off and there will be acoustic screens around the work when its noisy

WORKS

  • Project is to waterproof roof of Leisure centre and address levels outside the sports hall so that water no longer ponds
  • The waterproofing product will have a 15 year guarantee
  • All paving slabs will be lifted, numbered and stored on the grass area

SERVICES

  • Site accommodation will be in underground carpark
  • Site storage will be at the end of Basterfield Service Road
  • They will be using electrical equipment where possible and recharging them overnight at the leisure centre

COMMUNICATIONS

  • There will be 2 site noticeboards with information about the works and the contact numbers of the PM and site supervisor. If there is an issue call them in the first instance
  • They will be advising about when things are happening and they are looking at having a weekly email update and notices on all the notice boards

contact details

Ehsan Fathiazar Project Manager: ehsan.fathiazar@volkerlaser.co.uk 07385 945853
Paul Lonergan Site Manager: paul.lonergan@volkerlaser.co.uk 07876 876085